Precast concrete house price in Catalonia: calculator and examples
The price of a precast concrete house (detached, 100 to 250 m², standard quality) is around €2,150–2,550/m² + VAT in the Barcelona area; for a terraced house, €1,800–2,150/m² + VAT. A 150 m² house on two floors comes to about €345,000 + VAT. This is an indicative estimate for the finished house, not the kit.

Free and without leaving your details: you see the price straight away. Already have a plot? Work out the fees for your project.
Free calculator
How much does it cost to build your house?
Answer three questions to see the indicative contract price (what a building contractor would charge you), floor by floor. At the end we can send it to you as a PDF to keep.
Your house, floor by floor
Start with the ground floor. If your house has more floors, a garage, a basement or a porch, add them: they do not cost the same as the living space.
Where are you going to build?
We use the town to work out the price zone. The site and the foundations add the cost of retaining walls, earthworks and special foundations.
Finishes and bathrooms
After floor area, the quality of finishes and the number of bathrooms have the biggest effect on the price.
Construction price of your house
Contract price excl. VAT
–
Rounded figures.
Indicative price for building the house. To see what it includes, what it does not and how it was calculated, we recommend downloading the PDF. Based on the COAC reference module method (Architects’ Association of Catalonia), with Kaitek’s own adjustments; it is not an official COAC tool.
What next?
Tell us where you are and we will suggest the next step.
Work out the fees for your project
Outline design from €2,600 + VAT (house of about 100 m² in Barcelona). We work in stages: if the outline design concludes that the house is not feasible, you do not have to commission the following stages.
Before you buy, check what can be built. Planning rules (buildable area, height, setbacks) decide whether your house fits on that plot. An hour with an architect can save you from a bad purchase: €90 + VAT for the first hour, at our office, by video call or by phone.
Book a consultation with an architectGet your estimate as a PDF
With the breakdown, what is and is not included, and what you still need to add for the total investment. We will send it to you by email.
How we calculate the price
We start from the COAC basic module for 2026 (€677/m²; COAC is the Architects’ Association of Catalonia) and calibrate it with market prices (×1.40). Then we apply the coefficients for zone, façades, quality and use, add the extras for site and bathrooms, and add 19% for overheads (13%) and contractor’s profit (6%). The result is a contract price: what a building contractor would charge for the finished house, excluding VAT.
- Zone (the calculator assigns it from the town): Barcelona area ×1.00; rest of Barcelona province, Girona, Tarragona, Lleida city, Cerdanya, Val d’Aran, Alta Ribagorça and Alt Urgell ×0.95; rest of Lleida and Terres de l’Ebre ×0.90.
- Façades: detached ×1.20; end of terrace (semi-detached or corner) ×1.10; terraced ×1.00.
- Quality: Standard ×1.00; High-end ×1.20.
- Use: the house ranges from ×1.80 (up to 90 m²) to ×1.60 (250 m² or more), plus 5% if it is all on the ground floor.
Example, a 150 m² detached house on two floors in Barcelona: 150 m² × €677 × 1.40 × 1.20 (detached) × 1.70 (150 m² house) gives about €290,000 of construction cost (PEM), excluding VAT. Times 1.19, about €345,000 + VAT, with a range of €311,000 to €380,000 + VAT.
Kaitek is an architecture practice, not a building contractor: the actual price comes from the construction design and the contractors’ bids.
Price per square metre
How much does a precast concrete house cost per m²?
A detached house of 100 to 250 m² costs about €2,150–2,550/m² + VAT in the Barcelona area. The larger the house, the lower the price per m².
Assumptions: Barcelona area, detached house, standard quality, flat site, simple foundations and bathrooms included.
| Floor area | Price excl. VAT | €/m² excl. VAT |
|---|---|---|
| 60 m², one floor | €153,000 | 2,560 |
| 70 m², one floor | €179,000 | 2,560 |
| 80 m², one floor | €205,000 | 2,560 |
| 100 m², two floors | €241,000 | 2,410 |
| 120 m², two floors | €284,000 | 2,370 |
| 150 m², two floors | €345,000 | 2,300 |
| 200 m², two floors | €447,000 | 2,230 |
| 250 m², two floors | €541,000 | 2,170 |
Figures from the calculator on this page for the middle scenario; the range is ±10%. On a single floor the house costs 5% more, because it has more foundations and more roof: 150 m² on one floor, about €362,000 + VAT.
Detached, semi-detached or terraced
The fewer façades facing outside, the less the house costs. Prices excl. VAT, house on two floors:
| Floor area | Detached | End of terrace | Terraced |
|---|---|---|---|
| 100 m² | €241,000 | €221,000 | €201,000 |
| 150 m² | €345,000 | €316,000 | €288,000 |
| 200 m² | €447,000 | €409,000 | €372,000 |
| 250 m² | €541,000 | €496,000 | €451,000 |
End of terrace: semi-detached or corner house, with three façades. Barcelona area, standard quality, flat site, simple foundations and bathrooms included.
Why do other websites show lower prices?
Many adverts give module or kit prices: factory-made structure and façades, often without foundations, transport, assembly, services or finishes. Others are averages for the whole of Spain. Our figure is for the finished house in Catalonia, including the contractor’s margin; that is why it is higher.
| Item | Module or kit advert | Finished house |
|---|---|---|
| Structure and façades | Yes | Yes |
| Transport, crane and assembly | It depends | Yes |
| Foundations | Usually not | Yes |
| Services, bathrooms and finishes | It depends | Yes |
| Contractor’s overheads and profit | It depends | Yes |
| Permit, fees, utility connections and land | No | No |
Always compare like with like: what each price includes and whether VAT is included.
Factors
What drives the price of a precast concrete house
We start from a 150 m² detached house on two floors in the Barcelona area, standard quality, flat site, simple foundations and bathrooms included: about €345,000 + VAT. This is what happens if you change one thing:
| If you change… | Price excl. VAT | Difference |
|---|---|---|
| Girona, Tarragona or rest of Barcelona province (×0.95) | €328,000 | −€17,000 |
| Rest of Lleida or Terres de l’Ebre (×0.90) | €311,000 | −€34,000 |
| End of terrace | €316,000 | −€29,000 |
| Terraced | €288,000 | −€57,000 |
| High-end quality | €414,000 | +€69,000 |
| All on one floor | €362,000 | +€17,000 |
| Gentle slope | €350,000 | +€5,000 |
| Steep slope | €361,000 | +€16,000 |
| Semi-deep foundations | €350,000 | +€5,000 |
| Micropiles | €365,000 | +€20,000 |
| Steep slope and micropiles | €381,000 | +€36,000 |
| 30 m² garage (basic quality) | €378,000 | +€33,000 |
| 60 m² basement | €436,000 | +€91,000 |
| 20 m² covered porch | €368,000 | +€23,000 |
| One extra bathroom | €350,000 | +€5,000 |
| One WC | €348,000 | +€3,000 |
Differences between figures rounded to the nearest thousand.
Floor area and floors
Up to about 90 m² the price per m² barely changes; beyond that, the larger the house, the lower the price per m². Below 45 m² of living space the calculator gives no figure, and below 60 m² it shows a warning. Above 400 m² in total, ask for a bespoke study.
Zone
The calculator assigns the zone from the town, among the 947 towns in Catalonia. Outside the Barcelona area, the price drops by 5% or 10%.
Façades
A detached house has more façade and more roof per m²: it costs 20% more than a terraced one, and an end-of-terrace house 10% more. A terraced house must also meet the sound insulation requirements towards the neighbours.
Finishes
High-end quality makes construction 20% more expensive. For the garage and the basement the calculator suggests basic quality, which you can change.
Site and foundations
A flat plot with good ground allows simple foundations, the calculator’s default. A slope or weak ground makes the ground floor more expensive. The geotechnical survey decides which foundations are needed, under the Spanish Building Code (CTE).
Garage, basement, porch and bathrooms
In basic quality, the garage costs at most half as much per m² as the house; the non-habitable basement 40% more than the garage; and the covered porch half as much as the house. The price includes 1 bathroom in houses under 90 m², 2 up to 160 m² and 3 above that.
Worked example
Example: 150 m² house with garage and porch
Detached house in the Barcelona area: 150 m² of living space on two floors, a 30 m² garage in basic quality and a 15 m² covered porch. Flat site and standard quality.
| Part | Price excl. VAT |
|---|---|
| House, 150 m² | €345,000 |
| Garage, 30 m² (about €1,100/m²) | €32,000 |
| Covered porch, 15 m² (half the house’s €/m²) | €17,000 |
| Total | about €395,000 |
| With 10% VAT, if you are a self-builder | about €434,000 |
The parts are rounded to the nearest thousand; the total comes from the full calculation.
Total investment
What else to add to the construction price
The estimate is the finished, assembled house: foundations on a flat site, structure, façades, roof, services, finishes at the chosen quality, the included bathrooms, and the contractor’s overheads and profit. For the total investment, add:
| Item | What to bear in mind |
|---|---|
| VAT | If you are building your own home, construction can carry 10% VAT. Professional fees always carry 21%. |
| Fees | Design, permit and site supervision, plus 21% VAT. We explain what an architect’s fees include. |
| Building permit and ICIO | The ICIO (construction tax) is up to 4% of the construction cost, depending on the town, plus the permit fee. |
| Preliminary surveys | Topographic and geotechnical surveys of the plot. |
| Utility connections and outdoor works | Water, electricity and drainage; landscaping, fences or a pool; use of the public road for the crane. |
| First-occupation habitability certificate | When the works are finished you need the first-occupation habitability certificate (cédula de habitabilidad), or the first-occupation licence depending on the town, to live in the house and connect the utilities. |
| Land | Purchase of the plot, notary and land registry. |
If you build a single home for yourself, the Building Act (LOE) does not require ten-year structural insurance unless you sell it within ten years. Many banks ask for it anyway for a self-build mortgage.
Building system
Panels or modules: the system and the works
There are two main precast concrete house systems:
- Load-bearing panels: concrete walls, solid or sandwich-type with the insulation inside, and hollow-core or precast slab floors. It allows a bespoke design. It is the system used in the precast concrete house we designed in the Maresme.
- 3D modules: complete sections of the house. Transport width and weight limit the design.
If you are unsure which system to choose, we explain the difference between a prefabricated and an industrialised house.
The pieces arrive on low-loader lorries and are lifted into place with a large mobile crane. Before deciding, check the access: narrow or steep streets, overhead cables, room for the crane and a permit to use the public road. With poor access or a distant factory, prefabrication loses its advantage.
The house has to be nearly zero-energy. In precast concrete, the critical point is the thermal bridges at the joints between panels: they are solved in the design, not on site.
Prefab or traditional
Is a precast concrete house cheaper?
The construction cost is usually similar to a traditional house. The difference is on site: assembly is shorter and factory production usually reduces surprises. Prefabrication shortens the works, though, not the permit process.
In the Maresme house, the structure and façades were assembled in four weeks. Prefab works less well with complex shapes, few repeated pieces or poor access. We explain this in more detail in is a prefabricated house cheaper?
How we work
From price to design: we work in stages
To build a precast concrete house you need a design signed by an architect and a building permit, as for any house. We coordinate the design with the manufacturer’s engineers, who calculate the panels; we prepare the bill of quantities so you can compare bids from several contractors on the same scope; and we supervise the works. Find out about our new-build service.
We work in stages:
1. Feasibility and outline design
We check what the plot allows and define the house.
2. Basic design and permit
The document used to apply for the building permit from the town council. We explain the difference between the basic and construction designs.
3. Construction design
Construction details and quantities to request bids.
4. Site supervision
Following the manufacturing, assembly and finishes.
The outline design costs from €2,600 + VAT for a house of about 100 m². The generator gives the price for your case straight away.
Still looking for a plot? Before you buy it, check what can be built on it in a consultation with an architect: €90 + VAT for the first hour.
Practice founded in 2009 · architects registered with the COAC · professional liability insurance with ASEMAS · Rated 4.9 out of 5 on Google · Barcelona and surrounding area. Kaitek is an architecture practice, not a building contractor: we do not build or sell houses.
Frequently asked questions
Frequently asked questions about the price of a precast concrete house
Have a plot? Ask for a quote for your project
Request the fee proposal in the generator: you get the price straight away. If you first work out your house and choose “I already have a plot”, the generator opens with your details and you also receive the estimate as a PDF.
Looking for a plot? Consultation with an architect: €90 + VAT for the first hour. Phone +34 93 685 22 85.